City of Perth Library and Public Plaza

Australia

Project Overview 

The Public Library and Plaza Project is to be built by the City of Perth on the site currently adorned by the Law Chambers building on Hay Street. The project consists of two separate components; a seven-level library building and a public plaza. The library also consists of an additional two existing basement levels which are to be refurbished.

TBH’s Role

TBH was engaged by Doric Group to provide detailed tender programming and 4D construction planning services. The level of detail that TBH was able to convey in terms of time planning and construction methodology enabled the client to showcase their understanding of this complex project and enhance the probability of winning a highly competitive tender.

The greatest challenge in providing time planning services was defining the construction methodology for this complex building, especially in relation to the confined site access and limited laydown areas available. The number of stakeholders working on adjacent sites also added a layer of complexity as the works on each of these separate projects converge at various times during construction.

The 4D construction planning presentation, with voice over, was used to demonstrate the construction methodology and was linked to the programme. Key milestone dates were highlighted on the monthly time bar below, along with a building section showing the internal fit out and other works.

Doric Group were successful in their tender and the project is currently under construction

To find out more about TBH’s Planning & Scheduling experience, please visit the Planning & Scheduling page.

Project Overview

Client Doric Group
Services Tender Programming & 4D Construction Planning Services
Value $55 million
Duration 2014
Speak to Our Experts