Sydney Water Upper South Creek

Project Overview

Client Sydney Water – Upper South Creek
Services Integrated Project Controls, Planning and Scheduling, Risk Management
Value $1.2 Billion
Duration 2022 - Present

Project Overview

TBH were awarded the integrated project controls (IPC) services and delivered these functions throughout the delivery phase. TBH’s engagement consisted of 2 stages, with a rapid Establishment phase to take over the existing IPC functions and develop connections with key stakeholders. After the Establishment phase, the second stage involved an uplift in the maturity of IPC capabilities to be suitable for a $1b+ project, providing proactive controls of the USC project. TBH’s key IPC functions included Time, Cost, Change, Risk, Document Management, Reporting and Governance together with a senior lead to interface with the broader Sydney Water business. Sydney Water’s pioneering use of the NEC4 form of contract on USC meant that the IPC functions had to be customised to provide the proactive time and cost analysis to support this collaborative commercial model.

TBH’s Role

TBH were awarded the integrated project controls (IPC) services and delivered these functions throughout the delivery phase. TBH’s engagement consisted of 2 stages, with a rapid Establishment phase to take over the existing IPC functions and develop connections with key stakeholders. After the Establishment phase, the second stage involved an uplift in the maturity of IPC capabilities to be suitable for a $1b+ project, providing proactive controls of the USC project. TBH’s key IPC functions included Time, Cost, Change, Risk, Document Management, Reporting and Governance together with a senior lead to interface with the broader Sydney Water business. Sydney Water’s pioneering use of the NEC4 form of contract on USC meant that the IPC functions had to be customised to provide the proactive time and cost analysis to support this collaborative commercial model.

Planning and Scheduling

• Development of SW Master Schedule for AWRC, Pipelines and Access Road
• Review and comments on contractors’ schedules
• Review of contractor’s EOT
• Analysis on productivity rate and identify gaps
• Establish Earned Value reporting

Cost Estimating and Management

• Development of CBS and cost tracking tool
• Development of detailed SW team estimate
• Consolidate contractor’s contract price into budget
• Create and alignment of WBS and CBS to implement Earned Value progress measurements
• Development of risk adjusted cashflow forecasts
• Review and inputs into Early Warnings and Change Events

Risk Management and Analysis

• Development of Risk Register
• Fortnightly risk review sessions to review and maintain mitigation actions
• Quarterly Cost and Schedule Risk Analysis
• Monthly contingency drawdowns and alignment with EWNs and CEs

Document Control

• Send and receive project documents to contractor
• Coordinate and respond with Comment Tracking Registers

Integrated Project Reporting

• Development of PowerBi Dashboards covering metrics for time, cost, risk, change, KPIs, safety