Image

Recommendations for projects affected by current Greater Sydney & Adelaide Construction Industry Shutdown

Whilst the effect of the Greater Sydney and Adelaide construction shutdown is immediate and profound, the lasting impacts on each project will of course depend on a range of factors which will come to light in the coming days and weeks, for example:

  • Duration of the shutdown;
  • Effect on supply chains (eg delivery uncertainty / manufacture pauses / storage costs / transport re-scheduling / supplier re-prioritisation of Sydney and Adelaide projects);
  • Effect of any staged or partial re-opening strategies (eg productivity impacts and resource reallocation if certain projects are prioritised);
  • Acceleration costs for projects striving for predetermined “hard” completion dates;

Our current recommendations for affected projects:

Initial actions 

1. Establish and agree the basis for contractual entitlement for recovery of cost and time applicable to the current situation;

2. Understand contractual time periods for notification of events giving rise to delay and cost – these should be adhered to for the benefit of all parties, notwithstanding the unprecedented nature of this event.

Time 

1. Review the requirements of the Contract regarding delay:

  • Notice of Delay clauses
  • Extension of Time clauses – their operation, and obligations of the parties;
  • Ongoing notice provisions

2. Establish the status of the works (and the true critical path) at the commencement of the delay;

3. Continue to update the status of the works regularly throughout the delay – considering the full scope of the work under the Contract, including all off-site activities;

4. Start to consider the effect of any work that may be required relating to re-start of the work (site re-establishment);

5. Commence planning to minimise the impact of lost time – consider mitigation obligations, as distinct from acceleration proposals or instructions.

Cost

1. Quantify and record actual costs related to the shutdown as they occur, for example:

  • Demobilisation costs;
  • Site protection / security;
  • Additional storage costs

Ideally isolated from other costs so they can be readily identified.

2. Start to consider:

  • The cost of any work that may be required relating to re-start of the work (site re-establishment);
  • Costs arising from lost productivity during ramp-up;
  • The cost of any acceleration under consideration.

We will update our advice as the situation unfolds.

If you’d like to learn more about TBH’s Claims and Dispute Resolution service, please visit this page.

    Speak to Our Experts

    If you'd like to know more about how TBH can help your project, please use this form to get in touch with one of our industry-recognised experts.

    Speak to Our Experts